London's Pulse: Medical Officer of Health reports 1848-1972

View report page

London County Council 1911

[Report of the Medical Officer of Health for London County Council]

This page requires JavaScript

182
Annual Report of the London County Council, 1911.

South of the Thames.

Main Drainage Extension Scheme find additional works in connection therewith.

Southern outfall sewer enlargement and Southern high-level sewer. No. 2—£s.d.
Sections A-D—Completed at cost of723,3091710
Greenwich-road branch—
Section 1—Completed at cost of12,808101
„ 2—Contract price22,79663
Southern high-level sewer, No. 2—
Section E —Completed at cost of361,22354
,, (extension)—Contract price88,398149
Deptford pumping station—
Erection of additional engine house (exclusive of machinery)—Completed at cost of46,33000
Machinery, etc.29,380100
Crossness pumping station—
Erection of additional engine house—Contract price63,689185
Machinery—Estimated cost22,00000
Flood Relief Scheme.
Wandsworth and Battersea relief sewer—Completed at cost of38,4521911
Falcon Brook pumping station—Completed at cost of20,69550
Bermondsey and Southwark relief sewer—Completed at cost of99,330176
Shad Thames pumping station—Completed at cost of39,740710

Local sewers.
The figures quoted above do not include the cost of purchasing property required, of settling
claims for compensation payable by the Council of purchasing and fixing machinery, etc., or of
employing the necessary supervising staff, etc.
Section 69 of the Metropolis Management Act, 1855, provides that no new local sewer shall be
made without the previous approval of the Council.

The subjoined table shows the total length and sizes of the local sewers, the construction of which was sanctioned by the Council during the year.

Size.North of Thames. feet.South of Thames. feet.Total length. feet.
4 ft. by 2 ft. 8 in.1,6051,605
4 ft. by 2 ft. 6 in.150-150
3 ft. 3 in. by 2 ft. 2 in.-260260
1 ft. 6 in.1,0134621,475
1 ft. 3 in.2,545(1)3,193(2)(5)5,738
1 ft.2,675(3)6,976(6)9,651
9 in.7,026(4)(7)8,970(8)15,996
6 in.167665(9)832
Total16,18120,52636,707

(1) Including 495 feet in lieu of existing sewers.
(2) „ 18 feet „ „ „
(3) „ 578 feet „ „ „
(4) „ 1,250 feet „ „ „
(5) „ 1,560 feet reconstruction.
(6) „ 820 feet „
(7) „ 365 feet „
(8) „ 185 feet „
(9) „ 205 feet surface Water sewer.