The footways Yeoman-street have heen flagged with York paving, under the provisions
ofthe 78 sec. of the 25th and 26th Vic. c. 102, and the cost apportioned in the following
manner:- Yeoman Street.
Cost of Work 145 4 10
Amount paid by Owners and Occupiers 86 9 9
Amount contributed by Vestry 58 15 1
The carriageway, Deptford Old-road, at Elizabeth-place, lias been reformed to meet the
approach to the East London Railway Bridge ; the curbing of the said road to the boundary
of the parish beyond Midway-place has also been completed.
The bridges and approaches thereto, over the East London Railway at Deptford Lowerroad,
Westfield-terrace and Cross-street, having been upon inspection found to be properly
constructed, made up and paved the Vestry have taken the carriageways and footways
thereof under their control for future maintenance, cleansing, &c.
York paving has been laid on the West side of the Deptford Lower-road from the
" Prince of Orange" southward, to join the paving laid by the East London Railway Companv
on the approach to their bridge; the old York paving of the east footway near the China
Hall P.IL, has been reinstated with new, and a pitched crossing 5 feet wide formed in the
carriageway, from the corner of Bristol-terrace, across to the point where the Deptford-road
and the Deptford Old road intersect by the East London Railway Station.
The footway on the south side of the Plough-road between Deptford Lower-road and
the bridge, has been paved with York stone and the curb relaid; the footways, Plough-road,
northward of Plough-bridge, have also been paved and completed.
Plough Road Improvement.
The Vestry have affected an exchange of land with the Surrey Commercial Dock
Company on the east side of the Plough-road, and at the north-east corner of the approach to
Plough Bridge-road, for the improvement of the line of footways and carriageways at those
points, the Dock Company having agreed to pay to the Vestry the sum of £20 for the land
taken into the Dock premises, over and above the area thrown into the public way. The
carriageway of the east approach to Plough-bridge has been raised and altered, in order to
lessen the gr adient of the incline.
I carriageway ofthe north approach to the Lady Dock Bridge, Commercial Dock-road,
nas also been raised and improved, and York paving substituted for the old pitcher paving in
the east footway at that spot.
Paving Jobbing Works.
A Contract has been entered into with Mr. Lewis Etheridge, for the execution by him of
the paving jobbing works at a schedule of prices, in lieu of the same being done by paviors
masons employed by the Vestry as heretofore.
The carriage paving in the narrow way Rotherhithe-street, by Swan-lane, has been taken
up and relaid.

The following is a statement of applications made to the Vestry to drain houses and premises, and the results consequent thereupon:—

Number of Notices received.No. of houses permanently drained into covered sewers.No. of New houses temporarily drained into Cesspools.Buildings and premises other than houses drained.House drains cleared.Total Number of Houses, and Buildings inspected for drainage.
39514684109