[Report of the Medical Officer of Health for Fulham]
This page requires JavaScript
54
of a different construction, size, material, or other conditions, or in
another manner or form than shall be directed or appointed by the aforesaid
District Board; every person so offending, shall for every such
offence, forfeit a sum not exceeding Fifty Pounds; and the Board
may cut of the connexion with such sewer.—Penalty: 25 and 26
Vic. Cap. 102, Sec. 61.
VI. The person or persons making application under these Regulations will be
required to lodge a sum sufficient to meet the expenses of the Board for
supervision of the Works, such sum to be fixed at the time of granting
the application.—See Note.
Any further information required, and forms of application for permission to
construct sewers, etc., may be obtained of the Surveyor at the Offices of the
Board.
Approved, and ordered to
be printed, 4th April, 1877.
By Order,
THOMAS EDWARD JONES,
Clerk to the Board.
Broad-way House,
Hammersmith, W.
REGULATION No. VI. amended by addition of words following.
Note.—That when the plans are approved, the owner or builder of the Sewer
as the case may be, shall give to the Surveyor to the Board seven days' notice (in
writing) of the date of his intention to commence, and of the quantity of work
he intends to execute under such notice; and to deposit a sum equivalent to one
guinea per week, or such other sum as may be considered necessary, for so many
weeks as the works may be in progress; and if such time be exceeded, then a
further notice shall be given and further sum shall be paid at the same rate.
Should the work be discontinued or stopped from any cause, previous to commencing
the same, a fresh notice shall be given, and payments made as aforesaid.
Approved, and ordered to
be printed, 9th July, 1877.
THOMAS EDWARD JONES,
Clerk to the Board.