£ | s. | d. | £ | s. | d. | |
---|---|---|---|---|---|---|
Brought forward | 8,069 | 14 | 0 | |||
South Street—East Side, from Dean's Buildings to Northampton Street. | ||||||
1,125 ft. sup. Victoria Stone Paving | 37 | 10 | 0 | |||
96 ,, lin. New Edge Kerb | 6 | 16 | 0 | |||
96 ,, „ Kerb Reset, &c. | 1 | 12 | 0 | |||
4 yds. cube Concrete | 2 | 14 | 0 | |||
48 | 12 | 0 | ||||
South Street—West Side, from East Street to Stables. | ||||||
909 ft. sup. Victoria Stone Paving | 30 | 6 | 0 | |||
129 „ lin. New Flat Kerb | 12 | 7 | 3 | |||
3 yds. cube Concrete | 2 | 0 | 6 | |||
44 | 13 | 9 | ||||
South Street—East Side, from Aylesbury Street to No. 115. | ||||||
261 ft. sup. Victoria Stone Paving | 8 | 14 | 0 | |||
90 „ lin. New Edge Kerb | 6 | 7 | 6 | |||
9 yds. cube Concrete | 6 | 1 | 6 | |||
21 | 3 | 0 | ||||
Steedman Street—both sides, from Crampton Street to Railway Bridge. | ||||||
3,906 ft. sup. Victoria Stone Paving | 130 | 4 | 0 | |||
300 „ lin. New Flat Kerb | 28 | 15 | 0 | |||
300 „ „ Kerb Reset | 10 | 0 | 0 | |||
14 yds. cube Concrete | 9 | 9 | 0 | |||
178 | 8 | 0 | ||||
Theobald Street—West Side, from Arnott Street to Standard Street. | ||||||
1,350 ft. sup. Victoria Stone Paving | 45 | 0 | 0 | |||
21 „ lin. New Edge Kerb | 1 | 9 | 9 | |||
240 ,, „ Kerb Reset, &c. | 4 | 0 | 0 | |||
5 yds. cube Concrete | 3 | 7 | 6 | |||
53 | 17 | 3 | ||||
Theobald Street—West Side, from Arnott Street to Boundary. | ||||||
1,017 ft. sup. Victoria Stone Paving | 33 | 18 | 0 | |||
39 ,, lin. New Edge Kerb | 2 | 15 | 3 | |||
186 „ ,, Kerb Reset, &c. | 3 | 2 | 0 | |||
5 yds. cube Concrete | 3 | 7 | 6 | |||
43 | 2 | 9 | ||||
Trafalgar Street—Both Sides, from Walworth Road to Portland Street. | ||||||
12,240 ft. Bup. Victoria Stone Paving | 408 | 0 | 0 | |||
801 „ lin. New Flat Kerb | 76 | 15 | 3 | |||
1,200 ,, „ Kerb Reset, &c. | 20 | 0 | 0 | |||
47 yds. cube Concrete | 31 | 14 | 6 | |||
536 | 9 | 9 | ||||
Carried forward | 8,996 | 0 | 6 |